9. 6. 2005 Grand Opening
There was a press conference and grand party to celebrate the festive and official opening of Budìjovická alej. A unique audiovisual show with Japanese touch took place on the 8th floor of Budìjovická alej, providing extraordinary view at Prague.
8. 6. 2005 Final Inspection Effective
The Final inspection became legally effective on 8 June 2005. Let´s celebrate!
20. 5. 2005 Final Inspection
We have successfully passed the final building inspection. Only few non-conformities were recorded and will be retrieved shortly.
10. 4. 2005 Welcome Shell!
We kindly welcome company Shell Czech Republic among our tenants in Budejovicka alej. Shell will occupy the entire 4th floor with 2,300 sq m. They are planning to move in end June 2005.
21. 3. 2005 First leases signed
Skanska Property is happy to announce the execution of two first Future lease contracts for Budejovicka alej. We kindly welcome SG Equipment Finance Czech Republic, s.r.o. (1,600 sq m) and Anect, a.s. (1,400 sq m) to our building. Both companies wish to move in already in June 2005. In the meantime, the whole 4th floor is under negotitation and we hope to welcome next tenant till the end of March 2005.
16. 2. 2005 Scafolding has been removed
The metallic facade of low building has been completed at the end of January and scafolding has been removed.
14. 2. 2005 Tower cranes left the site
Both tower cranes left the site.
7. 2. 2005 Show room is ready
The show room is ready for viewings and presentations. The first visitors commented the showroom in superlatives and everyone was surprised by unconventional approach of the developer.
31. 1. 2005 Facade works
The alucobond facade on the lower building is finalized and scaffolding was installed on the tower. Showroom is scheduled to be opened in two weeks and lease negotiations with future tenants shall be closed in few weeks.
22. 12. 2004 Christmas is coming
In order to provide the neighbors of the site with some Christmas quite time, Skanska is closing the site till the end of the year 2004. This will not cause any delay in the constructions, since this Christmas brake was planned in the construction time schedule.
20. 12. 2004 Topping-out Ceremony
We have reached the top of the building and in the afternoon hours there was a topping-out ceremony. All the members of construction team - investor representatives, site management and the workers gathered together to celebrate the crucial step in the construction.
14. 12. 2004 Interior works
The tenders for the inerior works have commenced.
7. 12. 2004 Site inspection
The kolaudace - site inspection - for the water building permits hase been succesfully completed on 25/11/2004.
26. 11. 2004 Showroom
The showroom concept has been agreed and the design finalized. Interior architect in close cooperation with the investor are in process of ordering the furniture. The showroom shall be opened for first visitors in the end of January 2005.
23. 11. 2004 Construction works
The construction works have been proceding in accordance with Master Programme. The sub contractors for facade works and roof water-proof insulation have been progressing with their work.
2. 11. 2004 Site works
The building reached 5th level above ground and all the work proceed according to the time schedule. Facade works have started and will continue for several months.
25. 10. 2004 Showroom
Architects, marketing and leasing experts and project team has focused on planning the showroom within the building. After some brainstorming the team has come with very innovative ideas and courages design. The project for the showroom will be finalized in one month and the realization will continue until January 2005. To be continued...
20. 10. 2004 Skanska Safety day
On 20 October 2004 all Skanska companies around the world carried out the Skanska Safety Day. Skanska strongly focuses on Health and Safety issues to reach NO-INJURY sites. The Safety Day was carried out successfully and we will do our best to keep the pace.
12. 10. 2004 Construction news
The mechanical, electrical and plumbing works have started. The site management team eliminated a short delay on the works on concrete frame, therefore we are very close to start the facade works. We are really looking forward to see the real outcomes of our architect's visions! The interior design is finalized now as well and you can soon expect update in this matter...
4. 10. 2004 Web camera
Watch us working! The site web camera is in place and online. You can see the daily developments on our construction site. To provide you with better overview we have created a history section where all weekly photos are saved. Looking forward to your comments!